Snowy Hydro will undertake a comprehensive review of its $12 billion Snowy 2.0 scheme as productivity and financial issues ...
It’s taken 10 years, blown out by hundreds of millions of dollars, and is still nowhere near becoming operational. Now there ...
Former prime minister Malcolm Turnbull commissioned Snowy 2.0 in 2017, declaring a completion deadline of 2021. But ...
Snowy Hydro chief executive Dennis Barnes will not estimate the potential final cost of the mega project, but says keeping ...
Australia’s multibillion-dollar plan to turn its tallest mountain range into a giant pumped-hydro battery faces new ...
Snowy Hydro says it will need to acquire more funds to deliver the Snowy 2.0 renewable energy project, as costs continue to spiral beyond the previous $10 billion blowout.
Snowy Hydro has been forced to order a comprehensive review of the $12bn Snowy 2.0 pumped hydro scheme as mounting ...
Snowy Hydro has directed Snowy 2.0 principal contractor Future Generation Joint Venture (FGJV) to undertake a comprehensive line-by-line reassessment of its costs to deliver Snowy 2.0, as the ...
Follow the latest news headlines from Australia's most trusted source. Read in-depth expert analysis and watch live coverage ...
How could a sophisticated, ostensibly responsible government have embarked on such a risky project without any serious ...
Snowy Hydro has directed Snowy 2.0 principal contractor Future Generation Joint Venture (FGJV) to undertake a comprehensive line-by-line reassessment of its costs to deliver Snowy 2.0, as the ...