2hon MSNOpinion
Snowy 2.0 cost blowouts might be OK if the scheme stored power more cheaply than batteries. But it won’t
As the cost of Snowy 2.0 rises yet again, defenders claim the scheme can store energy cheaper than batteries. But this ...
How could a sophisticated, ostensibly responsible government have embarked on such a risky project without any serious ...
Snowy Hydro has directed Snowy 2.0 principal contractor Future Generation Joint Venture (FGJV) to undertake a comprehensive line-by-line reassessment of its costs to deliver Snowy 2.0, as the ...
Snowy Hydro chief executive Dennis Barnes will not estimate the potential final cost of the mega project, but says keeping ...
Former prime minister Malcolm Turnbull commissioned Snowy 2.0 in 2017, declaring a completion deadline of 2021. But ...
Snowy Hydro will undertake a comprehensive review of its $12 billion Snowy 2.0 scheme as productivity and financial issues ...
Snowy Hydro says it will need to acquire more funds to deliver the Snowy 2.0 renewable energy project, as costs continue to spiral beyond the previous $10 billion blowout.
It’s taken 10 years, blown out by hundreds of millions of dollars, and is still nowhere near becoming operational. Now there are calls for the Darwin ship lift project to be scrapped.
Snowy Hydro has been forced to order a comprehensive review of the $12bn Snowy 2.0 pumped hydro scheme as mounting ...
Australia’s multibillion-dollar plan to turn its tallest mountain range into a giant pumped-hydro battery faces new ...
Snowy Hydro has directed Snowy 2.0 principal contractor Future Generation Joint Venture (FGJV) to undertake a comprehensive line-by-line reassessment of its costs to deliver Snowy 2.0, as the ...